BAC
Budget at Completion
What it actually means
The total planned budget for a work effort — the value the earned-value baseline sums to at the end. It's the yardstick that estimates at completion get compared against: EAC above BAC means the program currently expects an overrun.
Where you'll meet it
EVM reports; the denominator in most cost-health metrics.